The work is substantially completed as of March 30th for the 6 million dollar renovations to the Dance Building Facility.
The work included the replacement of the entire skylight glass, roof drainage and perimeter waterproofing and interior renovations including new resilient flooring, lounge area seating, painting and ADA accessible doors on the main floor and from the Plaza.
Final acceptance is pending the completion of contractor’s punchlist and receipt of skylight manufacturer’s warrantee.